Creative agency workflow: from enquiry to paid invoice

Eight stages, one owner each, and a rough duration for every one. Copy it, change the names, and run your next job through it.

5 min read

By · Updated

The short answer

A creative agency workflow is the same eight stages on every job: enquiry, quote, deposit, kickoff, production, review, delivery and paid invoice. Each stage has one owner and one exit condition. Write them down once and the studio stops reinventing the process on each project.

The durations below come from a typical small studio doing branding, motion or 3D work. Your numbers will differ. Replace them after three jobs.

The workflow at a glance

StageOwnerTypical durationExit condition
1. EnquiryFounder1 dayCall booked or declined
2. QuoteFounder1 to 3 daysQuote sent
3. DepositClient, then studio2 to 7 days50% deposit paid
4. KickoffProject lead1 dayBrief confirmed
5. ProductionTeam and freelancers1 to 4 weeksRound 1 delivered
6. ReviewClient, project lead3 to 10 daysVersion approved
7. DeliveryProject lead1 to 2 daysFinal files sent
8. Paid invoiceFounder14 days (net 14)Invoice marked paid

Read the table as a pipeline. A job leaves a stage only when its exit condition is true.

Who does what

Five roles cover a studio of six people. The same person often holds two.

  • Founder: enquiries, quotes, deposits, final invoice, the client relationship.
  • Project lead: kickoff, the ticket list, the quality check before the client sees anything.
  • Designer or artist: tickets in production, uploads of each version.
  • Freelancer: one or two tickets, usually for 1 to 3 weeks, with their own brief extract.
  • Client contact: one named person who sends feedback and approves.

Write the names next to each role on the project page. When a ticket stalls, the page shows whose turn it is.

Stage 1Enquiry

A form on the website feeds a list of prospects, each with a status such as New, Contacted or Qualified. The founder replies within a working day. A 20-minute call checks budget, deadline and fit.

Decline early when the budget is off by half. A polite no on day one costs less than a discount on day twenty.

Stage 2Quote

The founder writes the quote from the call notes. It lists deliverables, two included revision rounds, a price, 50% deposit, net 14, and a valid-until date. Use the quote template if you do not have one. For how to set the numbers, see how to price a freelance project.

Send it as a proposal the client can sign online. A signed quote is the start of the job. A reply that says "sounds good" is not.

Stage 3Deposit

The deposit invoice goes out the day the quote is signed. Production starts when it is paid, not before. A studio that starts on a promise ends up chasing the balance and the deposit together. The guide on the deposit invoice has the wording.

Stage 4Kickoff

The project lead opens a project page with the quote, the brief, the deadline and the budget. A 30-minute kickoff call confirms the brief and names who on the client side gives feedback. One person, not four.

The kickoff meeting agenda covers the call. The output is a confirmed brief and a list of deliverables, each as a ticket with a due date.

Stage 5Production

The team works the tickets. Freelancers get a link to their own ticket with the brief extract and files. A designer, an animator and a freelance illustrator each see only what they need.

Rules for this stage:

  • One ticket per deliverable, with a due date.
  • Versions are stacked: logo_v001, logo_v002, logo_v003.
  • Render nights are planned. A 4K animation that needs 11 hours on the farm starts at 18:00 so review can happen at 09:00.
  • The lead checks the work before the client sees it.

Stage 6Review

The client comments on the work in one place. Round 1 and round 2 are included. A third round is billed at the day rate, as the quote says.

Each round has a deadline for the client's feedback, usually 3 working days. If feedback arrives late, the delivery date moves by the same number of days, and the lead says so in writing. More on cutting rounds in how to reduce revision rounds.

The exit condition is an approval of one named version. A click on Approve, or a reply that says "v4 approved", both work.

Stage 7Delivery

Final files go out in the formats the quote listed. Check the file names, the colour profiles and the licence terms. The project handoff checklist is the list to run.

Delivery and invoice go out on the same day. Do not wait for a quiet moment.

Stage 8Paid invoice

The balance invoice carries the project name, the PO number if the client gave one, and the due date, 14 days out. A reminder goes at day 15 if it is unpaid. The unpaid invoice follow-up guide has the wording for day 15, day 30 and after.

Mark the invoice paid by hand when the money lands. Then close the project.

Creative agency resource management for a small team

Resource management software plans who works on what across weeks. For two to ten people, a table does the job.

Make one row per person and one column per week. Put the job name in each cell and mark days off. A glance shows who is free in week 3. Update it on Monday morning.

Add three numbers per person: billable days available per week, days already booked, days left. A designer with 4 billable days a week and 3.5 booked has half a day. That is the answer to "can we take the packaging job".

When this table no longer fits on one screen, or when you bill by logged hours, look at a tool with resource planning. Studio capacity planning goes further, and for the tool question see creative agency project management software.

Workflow software: what it should do

Creative agency workflow software should show each job's stage, the next deadline and who owns it. It should keep the quote, the approval and the invoice on the job.

It does not need to automate every step. A small studio changes its process every few months, and a rigid builder gets in the way. OIO has no workflow builder or automations. It gives each job a page with tickets, a client link for comments and approval, and the invoice from the same project.

Run the first job through it

  1. Copy the table above into your notes and rename any stage.
  2. Take the next enquiry and put it through stage 1.
  3. At each exit condition, write the date in the project.
  4. After the job, compare your durations with the table and update it.

Questions

What is a creative agency workflow?

It is the fixed sequence of stages a job goes through, from enquiry to paid invoice, with an owner for each stage. A small studio can run eight.

How long does a typical creative project take?

Between 3 and 8 weeks for a branding or short animation job, counting quote, deposit and two review rounds. Your own history is a better guide.

Do small creative agencies need resource management software?

Rarely under ten people. A weekly table of people and jobs covers it until it stops fitting on one screen.

Should a deposit be paid before work starts?

Yes. 50% on signing is common. Start production when it is paid.