Archviz studio project management and pricing, from CAD files to final stills
An archviz quote is a promise about work you have not seen yet: the architect's files, the number of views and how many times the plan will change. Price the unknowns in the quote, then run the job so each one is recorded.
The short answer
Quote archviz per view for stills and per second for animation. Include a fixed number of revision rounds, price the rounds after that separately, and add a rush fee for work that has to be done faster than your normal schedule. Take a deposit before you open the architect's files. Then run the job in the same order as the quote: files in, cameras approved, first draft, feedback, finals, invoice.
This guide gives no market rates, because we found no public source for archviz rates that we could name. It gives the structure, plus an example with made-up numbers that you can replace with your own. For the base method of costing an image, read how to price archviz images.
What goes into an archviz quote
An archviz quote has five parts. If one is missing, you absorb the cost.
- The deliverables: how many views, at what resolution, in what format. "Four stills at 6000 by 4000 px, PNG and layered PSD" is a deliverable. "A set of renders" is not.
- The inputs you receive: DWG plans, a Revit or SketchUp model, material schedule, site photos. List them by version and date.
- The assumptions: the model is complete, the architect gives one set of comments per round, camera angles are approved before final render.
- The rounds: two included per view, the third billed.
- The money terms: deposit, milestones, rush fee, validity of the quote.
The free quote template gives you the layout, and how to write a 3D rendering quote walks through each clause.
Per image, per second, per project
There are three common ways to price, and each fits different jobs.
Per image. One price per view, usually higher for hero shots and lower for secondary angles. It suits stills for a brochure or a planning submission. The client can compare it with the number of views they want.
Per animation second. A price per finished second of a flythrough. It suits animation because render time grows with length. A 60-second flythrough at 25 frames per second is 1,500 frames. At 6 minutes a frame, that is 150 hours of render time. The per-second price needs to cover that machine time and the editing and sound. See how to price animation per second.
Per project. A lump sum for a package: 6 stills and a 30-second animation. It suits a client who wants one number. Break it down on the quote anyway, so a change in scope has a price already.
A worked example, with made-up numbers
This is an example to show the structure. The numbers are hypothetical. Use your own hourly cost.
A residential block, 6 stills and one 30-second flythrough, 8 weeks from files to delivery.
| Item | Basis | Amount |
|---|---|---|
| Hero exterior, dusk | 1 view | 2,100 |
| Street exterior, day | 1 view | 1,500 |
| Lobby | 1 view | 1,300 |
| Apartment living room | 1 view | 1,300 |
| Apartment kitchen | 1 view | 1,100 |
| Courtyard | 1 view | 1,200 |
| Flythrough, 30 seconds | 30 seconds at 160 | 4,800 |
| Subtotal | 13,300 |
The quote then says: two rounds per still and two on the animation animatic are included. A third round on a still is billed at 250 per half day, with a minimum of a half day. Changes to the building design after the model is approved are quoted separately. Rush: if the client asks for delivery in less than the agreed 8 weeks, add 25% to the affected items. That percentage is your own policy, not a market rate, so set it where your overtime costs you more.
Deposit: 30% of 13,300 is 3,990 before work starts. Milestones: 30% when the cameras and animatic are approved, 40% on delivery, net 14. See milestone payments for creative studios.
Revisions and rush fees in plain words
Write both in the quote, in the same plain language you would use on a call.
Revisions: "Each view includes two rounds. A round is one consolidated list of comments on one version. Comments that change the design of the building after model approval are not a round. They are a change order." The revision clause guide has sample wording.
Rush: "Delivery faster than the schedule in section 3 carries a 25% fee on the affected items. We confirm the new date and the fee in writing before we start." The point of the fee is to make the client choose. Most do not need the rush once they see the line.
Running the job, step by step
From the first file to the last still, this is the order that keeps a small studio out of trouble.
Step 1: files in
Ask for the CAD files in a named folder and check them the day they arrive. A typical drop: `TowerB_L03_plan_v04.dwg`, `TowerB_facade_v07.rvt`, `materials_schedule_2026-11-02.pdf`, site photos. Open each one. Check the units, the missing layers, the levels that are not modelled. Reply the same day with a list of what is missing. The clock on the quote starts when the files are complete, and you write that down.
Step 2: cameras before anything else
Send a clay render or a viewport capture of each camera, numbered C01 to C06. The architect approves the angles before you texture or light. A camera change after final render is the single most expensive change, because everything is redone.
Step 3: first draft
Send one set of draft renders with materials and light. Tell the architect what you want back: one consolidated list per view, with the view number on each line. Put the round count in the message: "View C02, round 1 of 2".
Step 4: feedback, in one place
Architect feedback arrives as marked-up PDFs, email lines, voice notes and a call. Turn all of it into a numbered list per view. Anything that changes the design goes onto a separate change list with a price. For more on handling this, see archviz client feedback rounds.
Step 5: finals and delivery
Render finals at the agreed size. Send the stills as numbered files, `C02_lobby_final_6000x4000.png`. Record the approval with the version and the date, and then invoice the last milestone. The full stage list is in archviz project management workflow.
Handling the architect
The architect is not always the person who pays you. Often the developer pays and the architect gives the comments. Find out at kickoff who approves, who pays and who can say no.
Ask the architect for one person to collect comments, and agree a response time of two working days per round. If a round takes ten days, the delivery date moves by eight, and you tell them on day three, not on day ten.
Architects change designs during the job, because the building is still being designed. That is normal. The quote has to say that changes to the building after model approval are priced as changes.
Where to keep all of it
Many small archviz studios use a spreadsheet for the quote, a folder for the files, email for the comments and an invoicing app for the money. It works with one job. With three jobs at once, nobody knows which version the architect approved.
OIO puts the job on one project page. Each view is a ticket with a deadline on the timeline. You upload each round as a new version on the ticket. The architect opens a link, with no account, and pins numbered comments on the render. A slider compares two versions. The architect clicks Approve this version, and OIO records who approved which version and when. A freelancer who models the furniture works from a link to their ticket and uses no seat. The quote and the invoices come from the same project.
Plans: Free for 1 project, Lite $5, Solo $19, Studio $99 for 5 seats, with a 7-day trial. Lite has no client tools, so review starts at Solo. OIO has no drawing on the render and does not read CAD files. See OIO for archviz studios.
Questions
How much should I charge for an archviz image?
Start from your hourly cost times the hours the view needs, add a margin, and round to a price you can say out loud. We found no public source for market rates, so we give a method, not a number.
How do archviz studios charge for animation?
Usually per finished second, or as a lump sum for a package. Render time grows with length, so check frames times minutes per frame before you set the price.
How many revision rounds should an archviz quote include?
Two per view is a common starting point. Write that a round is one consolidated list on one version, and bill the third at a day or half-day rate.
Should an archviz studio charge a rush fee?
Yes, if a faster schedule costs you overtime or a freelancer. Write the percentage in the quote and confirm the new date in writing before you start.
What files do I need from the architect to start?
Plans and elevations as DWG or PDF, a 3D model in Revit, SketchUp or IFC if it exists, a material schedule and site photos. List each file with its version and date.